Several major critical infrastructure projects under the Emergency Recovery Project 1 (ERP-1) are nearing completion, strengthening Sint Maarten’s resilience in areas like energy, emergency communications, and weather monitoring. The USD$5.1
More infoTrust Fund Moves Forward with Relaunched Bids for Schools, Gyms, and EOC
The National Recovery Program Bureau (NRPB) has recently relaunched the bidding processes for repairs to 12 school gyms and 13 public sports facilities, as well as the construction of the
More infoNV GEBE and NRPB begin final phase of installation of underground cables and waterlines
To strengthen the resilience of Sint Maarten’s electrical and potable water grids, N.V. GEBE and the National Recovery Program Bureau (NRPB) have been collaborating on underground installation activities and the
More infoNRPB Terminates Final Contract with Non-Performing Contractor under ERP-1
The National Recovery Program Bureau (NRPB) terminated a third contract under the Emergency Recovery Project 1 (ERP-1), following the contractor’s failure to mobilize for the planned expansion of the Emergency
More infoSchool gym and sports facilities repairs transition to new implementation plan
Contracts terminated; stakeholders informed as planning continues for alternative implementation options Philipsburg, Sint Maarten – The National Recovery Program Bureau (NRPB) has formally terminated the contracts for the repair of
More infoNRPB, Minister VROMI, and GEBE Sign $5.1M Agreement to Strengthen Utility Infrastructure in Four Districts
The National Recovery Program Bureau (NRPB), VROMI and N.V. GEBE have signed a US$5.1 million agreement to begin underground placement of mid-voltage electrical cables and potable water pipes in four
More infoMECYS & NRPB Sign Agreement to Begin Revitalization of Sint Maarten’s Sports Facilities
The Minister of Education, Culture, Youth, and Sport (MECYS) has formally handed over the first out of thirteen sport facilities under her authority by signing the respective repair agreements as
More infoRepairs Complete on 19 Schools as Trust Fund’s School Repair Activity Concludes
Philipsburg, Sint Maarten – 24th September 2024 – The National Recovery Program Bureau (NRPB) has marked a milestone in St. Maarten’s post-Hurricane Irma recovery with the completion of the school
More infoNew Emergency Vehicles Strengthen Sint Maarten’s Disaster Response
The National Recovery Program Bureau (NRPB) is announcing the delivery of a new fleet of emergency vehicles for the St. Maarten Fire and Ambulance Department, marking yet another milestone in
More infoNRPB clarifies misinformation about public tender for school gym repairs
Questions have been recently raised about a foreign company being awarded a contract by the National Recovery Program Bureau (NRPB) to repair twelve (12) school gyms, but much of the
More infoNV GEBE partners with Energynautics GmbH to enhance energy infrastructure and advance renewable energy initiatives
Philipsburg – NV GEBE is taking a significant step forward in its mission to modernize and sustainably transform its energy infrastructure by updating its business plan with support of Energynautics
More infoWastewater treatment system at Leonald Conner School fully repaired
The wastewater treatment system at the Leonald Conner Primary School in Cay Bay has now fully resumed operations, thanks to repairs through the Sint Maarten Trust Fund. Not many Sint
More info